Design Detailing · Denver, Colorado

Denver International Airport

Complex steel detailing for a landmark hotel and transit center.

LocationDenver, Colorado
ClientMiro Engineers
Structural steelMore than 2,300 tons

Project overview

Turning complex canopy geometry into fabrication-ready information.

The Denver International Airport project included a new hotel and commuter rail platform comprising more than 2,300 tons of structural steel. At the time, it was the largest project our team had delivered using the design-detailing process.

The defining elements of the structure were two exceptionally large and geometrically complex steel canopies. One is a freestanding canopy spanning more than 120 feet above the train platform. The second, larger canopy extends beneath the hotel and is integrated with the arches supporting the building above.

Project team and technical details
Engineer of Record
S.A. Miro, Inc.
General contractors
Mortenson, Hunt, Saunders
Primary scope
Structural steel detailing
Delivery approach
Design-detailing
Key structures
Hotel, commuter rail platform and two long-span canopies

Detailing scope

Delivery approach

01

Hotel and transit-center steel

More than 2,300 tons of structural steel were developed through the collaborative design-detailing process.

02

Freestanding train-platform canopy

A moment-welded diagrid canopy spanned more than 120 feet above the commuter rail platform.

03

205-foot integrated hotel canopy

The larger canopy continued beneath the hotel and extended beyond its north and south sides, integrated with the building’s supporting arches.

04

Diagrid joints and internal stiffeners

Complete joint penetration welds and multiple internal stiffeners were developed within complex, skewed connection conditions.

05

Fabrication sequence and welding access

Connections were reviewed in the shared 3D model with constructability, welding access and shop sequence in mind.

Model to field

Coordinating the Denver International Airport model for fabrication and field use.

Denver International Airport structural model01 / Coordinated model
Coordinated structural model for Denver International Airport.
Denver International Airport steel erection02 / Fabrication & field
Fabrication and construction context for Denver International Airport.

Technical complexity

Complex welded connections resolved before fabrication.

01

Congested welded diagrid joints

Several internal stiffeners converged inside individual joints at irregular angles, leaving limited space for complete joint penetration welds.

02

Skewed canopy geometry

Intersecting structural elements and non-orthogonal connections needed coordinated three-dimensional definition before fabrication release.

03

Canopy-to-hotel integration

The larger canopy had to remain coordinated with the hotel structure and its supporting arches as connection conditions developed.

04

Direct engineering decisions

The design-detailing workflow used the model to review difficult joints with the engineer, shortening successive RFI cycles and maintaining continuity through fabrication.

Our approach

Design-detailing that supported faster technical decisions.

Instead of relying exclusively on the traditional RFI process through the fabricator, the project used a collaborative design-detailing workflow. The 3D model became the primary environment for developing and coordinating complex connections with the engineering team.

Potential conflicts could be identified earlier, while difficult diagrid joints and stiffener arrangements could be reviewed before reaching the shop floor. This reduced the time normally required for successive RFIs and helped maintain continuity between engineering, detailing and fabrication.

One coordinated model for geometry, connections and constructability.

Both canopies use moment-welded diagrid systems designed to transfer structural loads across their surfaces and into massive supporting abutments.

The project’s complex geometry required close coordination between the engineering and detailing teams. Working within a shared 3D environment allowed connection conditions, internal stiffeners and intersecting structural elements to be evaluated before fabrication information was released.

This collaborative approach gave the project team greater visibility into difficult conditions and helped resolve constructability challenges directly within the model.

Project animation

Explore the project in motion.

Project result

A coordinated result delivered ahead of schedule.

According to the project team, the design-detailing process significantly improved the schedule. The collaborative 3D workflow provided a more direct way to address complex connection conditions than the traditional RFI-based process.

We believe this approach contributed to the project being completed approximately six months ahead of schedule.

“The project was an exceptional success. Having the 3D model and collaboration available with the Tekla team was a great asset to the project. The schedule benefited greatly from having Miro carry the detailing contract.”

Joe Rapp Engineer of Record, S.A. Miro, Inc.