Primary frame across seven zones
The 1,150-ton structural and miscellaneous steel package was organized into Erector Zones 1–7 for phased fabrication, delivery and erection.
Institutional/Public · Downtown Spartanburg, South Carolina
Coordinated steel detailing for a major public administration facility.
Project overview
The Spartanburg City–County Administration Building project involved a comprehensive structural and miscellaneous steel package for a new public administrative facility in downtown Spartanburg, South Carolina.
Working for SteelFab, our team detailed approximately 1,150 tons of steel. The scope extended beyond the building’s primary structure to include stairs, railings, access systems, support framing, bollards and perimeter lintels.
Detailing scope
The 1,150-ton structural and miscellaneous steel package was organized into Erector Zones 1–7 for phased fabrication, delivery and erection.
The scope included Stairs #1–#4, clock tower and maintenance stairs, and a ship’s ladder.
Railings were detailed for the lobby, council chamber, clock tower, plaza, exits, exterior areas and curbs.
Miscellaneous steel included removable and embedded bollards together with support framing for operable walls.
Angle lintels around the building perimeter were coordinated with their architectural locations and adjacent construction.
Deliverables followed fabrication priorities and planned erection progress, covering both structural steel and miscellaneous metals.
Technical complexity
Model information, review packages and material releases needed alignment with phased fabrication, delivery and installation.
Miscellaneous components were spread across public, service, exterior and clock tower areas, requiring location-specific coordination.
Operable wall supports, galvanized lintels, bollards and railings had to remain coordinated with the primary structure and adjacent construction.
The estimate comprised 2,223 structural hours and 689 miscellaneous-metal hours, requiring disciplined information management between the packages.
Our approach
Our detailing workflow treated the structural steel and miscellaneous metals as coordinated parts of a single building package.
The primary frame was developed according to the erection-zone sequence, while stairs, railings, access components and support framing were coordinated with their specific locations and adjacent systems.
This approach helped create clear, fabrication-ready information for SteelFab across the complete scope of work.
The primary structure was organized into Erector Zones 1–7. This division allowed detailing information to be aligned with the project’s planned fabrication and erection sequence.
Organizing the building into defined zones supported:
The zoned workflow provided a practical structure for managing the project’s 1,150-ton steel scope.
Project result
By organizing the main structure into seven defined erection zones, the detailing process supported an orderly progression from fabrication through delivery and field installation.
The combined scope represented an estimated 2,912 detailing hours:
The result was a comprehensive steel package covering both the building’s primary structure and the numerous secondary components required throughout the facility.